S/N
NAME OF PROJECT/CONTRACT
CLIENT
SCOPE
DURATION
1
PIPELINE CALL OUT CONTRACT LAND AND SWAMP, 30” x 56KM
WEST AFRICAN GAS PIPELINE (WAPCo0
REPAIRS
CALL OUT CONTRACT
2
PERMANENT OF TEMPORARY CLAMPED GAS PIPELINE
WEST AFRICAN GAS PIPELINE COMPANY (WAPCo)
CLAMPING AND INSPECTION
2 DAYS
3
10 INCHES SPLF TO MFS PIPELINE INSTALLATION
ADVANCE OIL PRODUCTION SYSTEMS LIMITED
PIPELINE INSTALLATION
4 MONTHS
4
PROVISION OF SERVICES
FOR WELDING JOINTS OF
” PIPELINE
WORK FROM SLN1 TO
ADAPALM 21KM
ADVANCE OIL PRODUCTION SYSTEMS LIMITED
PIPELINE INSTALLATION
5 MONTHS
5
36 INCHES
PIPELINE(GOLDEN TIE –IN) AT KP 104 OF ELPS II)
ZAKHEM/NIGERIAN GAS COMPANY LTD
TIE IN OF JOINT
ONE MONTH
6
SECTIONAL REPLACEMENT/PATCH WELDING/CLAMPING OF VARIOUS
DIAMETER/SIZE PIPELINE
HERITAGE PETROLEUM COMPANY (ANOTECH IN PATNERSHIP WITH OCEAN MARINE SOLUTION)
PIPELINE MAINTENACE
CALL OUT CONTRACT
(ON-GOING)
7
TRANS.NEMBE PIPELINER REPAIR NONWA PIPELINE SECTIONAL REPLACEMENT
ANASAMI/SHELL PETROLEUM DEV. COMPANY
SECTIONAL REPLACEMENT
FEB – APRIL, 2017
COMPLETED/
COMMISSIONED
8
TIE-IN OF 1 NO. 30” ESCRAVOS EXPORT PIPELINE PROJECT
GRAMEN PETROSERVE/CHEVRON NIG. LTD
CONSTRUCTION AND
EQUIPMENT PROVISION
CALL OUT PROJECT
COMPLETED/COMMISS
IONED
-
9
CONSTRUCTION OF THE DUAL 10” AND 6” PIPELINE PROJECT FROM
OWA-ALADINMA TO OGHAREFE
FLOWSTATION
PAN OCEAN CORPORATION
CONSTRUCTION
NOV. 2012 – AUGUST,
2018 COMPLETED/COMMISS
IONED
10
ESCRAVOS WELL 10LIMA FLOWLINE (2 NOS. 2.6KM X 4”)
ANASEMI CONSTRUCTION NIG. LTD SHELL PETROLEUM DEV. COMPANY
CONSTRUCTION
AUGUST – NOVEMBER,
2017
COMPLETED/COMMISS
IONED
11
SECTIONAL REPLACEMENT OF 24” ESCRAVOS –WARRI PPMC CRUDE PIPELINE
OCEAN MARINE SERVICES
SECTIONAL REPLACEMENT
CALL OUT CONTRACT
12
CUTTING AND REPLACEMENT 24” , 18” , 14”, 10” & 3” KADUNA REFINING & PETROCHEMICAL
KADUNA REFINING & PETROCHEMICAL COMPANY
CUTTING AND
REPLACEMENT OF PIPES
AUGUST –
SEPTEMBER, 2016 MONTHS
-
13
PATCH WELD OF TWO LEAK POINTS ON OBEN-SAPELE 18” OBEN – SAPELE GAS PIPELINE AROUND KP 25 OGHARAFE TOWN,
DELTA STATE
NIGERIAN GAS COMPANY EKPANWARRI
REPAIRS (PATECH WELD)
PPMC EMERGENCY PIPELINE PALLIATIVE MEASURE COMPLETED/COMMISSIONED
14
CUTTING AND REPLACEMENT OF 26” KRPC PIPE HEADER WESTERN BATTERY LIMIT IN AREA 3
KADUNA REFINING & PETROCHEMICAL
COMPANY
CUTTING AND REPLACEMENT OF PIPES
SEPTEMBER – DECEMBER, 2015 COMPLETED/COMMISSIONED
15
CALL-OUT CONTRACT FOR INSTALLATION /REPAIRS OF FLOWLINES /PILINES IN CHEVRON
NIG.. LTD. SWAMP LOCATION
CHEVRON NIG. LTD
PIPELINE AND FLOWSTATION REPAIR
CALL OUT CONTRACT
(2015-2015)
COMPLETED/COMMISS
IONED
16
OLERO BULKLINE REPLACEMENT PROJECT – MODIFICATION TO INTER-CONNECTING PIPE-BRIDGE (ICP) AND INSTALLATION OF PIG
TRAPS (RECEIVER, LAUNCHER,
PIPING SPOOLS AND STRUCTURAL
SUPPORT, ON THE NEW OLERO 16”
CHEVRON NIG. LTD
INTER PIPING INSTALLATION / FLOW STATION
CALL OUT CONTRACT
(2015-2015)
OMPLETED/COMMISSI
ONED
-
17
CONSTRUCTION OF OKPORHURHRU 6” BULKLINE, 4” FLOWLINE, AND
MANIFOLD
SEPLAT PETROLEUM DEV. COMPANY
PIPELINE CONSTRUCTION
JUNE-SEPTEMBER, 2011
COMPLETED/COMMISS
IONED
18
CONSTRUCTION OF DUAL 6”
SCHEDULE 80 X 1.5KM FLOWLINE AT ONA 4/5
PAN OCEAN OIL CORPORATION
CONSTRUCTION OF FLOWSTATION
1MONTH
COMPLETED/COMMISS IONED
19
CONSTRUCTION OF (SECOND
SEGMENT) SINGLE NPS 6 X 3.5 KM SCHEDULE 80 CARBON STEEL FLOWLINES FROM BOUNDARY POST (BP2.5) TO ASABORO-4
LOCATION
PAN OCEAN OIL
CORPORATION
CONSTRUCTIO N OF PIPELINE
1 MONTH
COMPLETED/COMMISS
IONED
-
20
26” ABITEYE-ESCRAVOS
CHEVRON NIG. LTD
REPAIR OF PIPELINE
COMPLETED/COMMISSI ONED
21
20” X 3.5KM PIPELINE
CONSTRUCTION
SHELL PETROLEUM
DEVELOPMENT COMPANY
CONSTRUCTIO N OF PIPELINE
COMPLETED/COMMISS IONED